A Bombshell at Burns Park, Literally
An update from St. Joseph Center of Arkansas — August 18th, 2026
For once, "bombshell" isn't an exaggeration. The hold on The Gardens at Burns Park is about actual World War II era munitions — and this is the story of how a unanimously approved community garden ended up waiting on a bomb squad.
For more than a year, St. Joseph Center of Arkansas has been working to build its new home at Burns Park. This is an update on where that effort stands, how we got here, and what comes next.
The short version: On August 17, 2026 the North Little Rock Parks & Recreation Commission voted to put The Gardens at Burns Park on hold until the U.S. Army Corps of Engineers completes a munitions survey and clearance of the site — a process the Corps estimates will take three to five years. Because our committed grant funding requires us to break ground by this October, and because our community of gardeners, farmers, and students cannot wait until 2029 or beyond, SJCA is now actively evaluating alternative locations, including sites outside North Little Rock.
How we got here
In March 2025, fire destroyed our historic building at the St. Joseph property in North Little Rock. That July, the Diocese of Little Rock notified us our lease would end January 1, 2026. Within a day, we reached out to the City of North Little Rock about the former RV campground site in Burns Park, and the Mayor publicly announced that the city was working with us on a relocation.
Our vision for the 47-acre site: expand the city's largest community garden from 50 to 100 plots, build a greenhouse , butterfly enclosure and garden, and market pavilion to host the North Little Rock Farmers Market, bring back our farm animals and education programs serving thousands of schoolkids, and a workshop for the Central Arkansas Master Naturalists, who maintain the trails in Burns Park and across Central Arkansas. SJCA committed to raising the money and building and operating the site at no cost to taxpayers or to the city.
The timeline
Date - What happened
Mar 19, 2025 - Fire destroys SJCA's historic building
Jul 31, 2025 - Diocese of Little Rock notifies SJCA the lease ends Jan 1, 2026
Aug 1, 2025 - SJCA contacts the City about the Burns Park RV campground site
Aug 7, 2025 - Mayor publicly announces the City is working with SJCA on a Burns Park relocation
Aug 28, 2025 - Draft proposal submitted to the Parks & Recreation Commission
Oct 8, 2025 - City Attorney raises Land & Water Conservation Fund (LWCF) compliance concerns
Oct–Nov 2025 - SJCA and city staff work through LWCF compatibility, with state and federal (National Park Service) review
Nov 17, 2025 - Parks & Rec Commission approves posting an request for proposal (RFP) for lease of the 47-acre site
Mar 16, 2026 - City issues the RFP
Apr 24, 2026 - SJCA hand-delivers its proposal, ahead of the Apr 28 deadline
Jun 15, 2026 - Parks & Rec Commission approves SJCA's proposal
Jul 17, 2026 - City notifies SJCA: the Corps will conduct a Formerly Used Defense Sites (FUDS) remediation, and no site work may occur until clearance
Jul 20, 2026 - A Corps representative tells the Commission clearance is an estimated 3–5 years out
Aug 17, 2026 - SJCA proposes to continue with a mitigation plan locating any ordnance and removing it from construction sites. Commission votes to hold the project until the Corps clears the site
Today - SJCA is actively evaluating alternative locations, including outside North Little Rock
What FUDS actually means: unexploded ordnance
Burns Park sits on land that was once part of the Camp Robinson military training grounds, where soldiers trained with live ammunition, artillery, and explosives during World War II. When the military left, not everything it fired was found. Some ordnance — shells, mortars, grenades — never detonated and may still be buried in the soil decades later. This is called unexploded ordnance, or UXO.
The U.S. Army Corps of Engineers tracks properties like this under its Formerly Used Defense Sites (FUDS) program, which identifies former military land and cleans up what was left behind. The former RV Park site is designated a Munitions Response Site within the Camp Robinson FUDS — meaning the Corps has flagged it for survey and removal of any unexploded ordnance that remains.
We want to be clear about what the Corps itself has said:
- The FUDS designation is a notification to the property owner, not a prohibition. It does not by itself stop development.
- The Corps performs clearance work in priority order. This site is Priority 2, with an estimated 3–5 years before crews survey and clear it.
- Decisions about use of the land in the meantime belong to the property owner — the City of North Little Rock.
This is also not new ground, in either sense: much of Burns Park sits on the same former training land, and golf, trails, soccer, and horseback riding continue there today. Working with hazard remediation professionals, SJCA proposed a mitigation plan — professional screening of any ground we disturb, following established UXO safety protocols to govern every phase of construction. The Commission chose instead to wait for full Corps clearance. We respect that safety was at the center of that decision.
What this means, and what's next
The hold has real consequences for our timeline. SJCA had the following funds committed: $10,000 from Whole Foods for 2026, $10,000 for 2027, $5,000 from Summit Utilities, $8,000 from the Sphinx Foundation, possibly $100,000 from USDA, and $45,000 from another national sponsor — all requiring the project to start by October. Our gardeners, our farmers, our students, and our community cannot wait three to five years for a home.
So while Burns Park remains the site we hoped for, we are now actively searching for other locations where possible.
Wherever we land, our mission doesn't change: growing food, farmers, and community.